Flughafen Frankfurt: Terminal 3

Challenge

Fraport AG plans to increase passenger handling capacity at Frankfurt Airport. To supplement the existing buildings in the north, Terminals 1 and 2, a new Terminal 3 is being built to the south of Frankfurt Airport on the site of the former US air base (now CargoCity South). Terminal 3 will be designed for a capacity of 14 million passengers per year.

Solution

The tasks include:

  • Installation of the emergency lighting system in the main terminal building, the PTS station, and in operations building 624
  • In addition to the main control center, a total of more than 100 substations, approx. 25,000 lights, and around 500 km of cables and wires were installed

Pictures: Fraport AG 

Client

Fraport Ausbau Süd GmbH